50 Howick Road Offices
TIMELINE
03 November 2023Site Establishment
We began by clearing and preparing the site, setting up essential services and creating a safe, organized base for our own office build.
15 November 2023Earthworks
Bulk earthworks and new retaining walls were completed to stabilize the ground and prepare the platform for construction.
23 November 2023Concrete Foundations
Reinforced concrete slabs were cast, providing the solid foundation needed to support our new office facility.
12 January 2024Back Wall Construction
The reinforced concrete slabs for both the front and rear sections of the building have been poured, and construction of the rear walls is now underway, forming the structure’s initial vertical elements.
19 January 2024Front Section Steel Frame
The steel framework and roof for the front section of the building have been completed, establishing the primary structural support and weatherproofing for this area.
29 January 2024First Floor Walls
Construction of the first-floor walls has begun, marking the start of the vertical expansion above the ground floor and defining the building’s upper-level layout.
12 February 2024Second Floor Preparation
Preparatory work is underway for the construction of the second-floor walls on the rear section of the building, setting out the structure for the upper level.
20 February 2024Building Connection
Preparations for the top-floor walls on the front building are underway, alongside the construction of the structural connection between the front and rear sections, integrating both parts of the facility.
15 April 2024Top Floor External Walls
Construction of the top-floor external walls for the front building is now complete, defining the full vertical envelope of this section.
29 April 2024Internal Walls & Fixtures
Work has commenced on internal walls and fixtures within the front building, shaping the interior spaces and beginning the fit-out process.
17 May 2024Rear Building Completion
Construction of the rear building’s walls is complete, and the roof has been installed, finalizing the main structural envelope of this section.
28 May 2024Window Installation
Windows are being installed throughout the building as internal construction and fit-out work continue, bringing natural light into the spaces and progressing towards a functional interior.
12 June 2024Exterior Painting
Exterior painting has commenced, while finishing touches and final construction works are being completed, preparing the building for practical completion.
30 June 2024Final Construction
The last construction elements and finishing details are being completed, bringing the building closer to full readiness for occupation.
August 2024Completed Office Building
After a period of final inspections and preparation, the building is now fully complete, showcasing the finished design and construction quality of our new offices.
October 2024Move-In
Our team has moved into the new office, setting up operations and bringing the facility to life as our fully functional headquarters.